PARISH COUNCIL: Severn Trent: Notification has been received that the planned works will now commence at the end of October not in August.

Sheepwash Bridge: This still requires repair and the county council will be contacted again.

Cleeve Road: It is hoped foundation work will be carried out this year and re-surfacing next.

Litter Bins: These are now in place.

Dog Fouling Bins: Wychavon to be contacted regarding this.

Queen's Golden Jubilee: Any monies remaining from these celebrations will be divided half each to Littleton School and for the provision of tables for use by village organisations.

Audit: This to take place on September 9.

Bus shelter: The estimate for re-repainting was accepted.

WRVS: It was agreed to make a grant of £25.